docs: update state after Phase 6 completion

This commit is contained in:
Christopher Mühl 2026-04-09 10:41:40 +02:00
parent 949d318ecb
commit 0c7af377f1
No known key found for this signature in database
GPG key ID: 925AC7D69955293F

View file

@ -2,16 +2,16 @@
gsd_state_version: 1.0
milestone: v1.1
milestone_name: Modes & Filtering
status: ready_to_plan
stopped_at: Roadmap created for v1.1 (Phases 6-10)
last_updated: "2026-04-08T23:00:00.000Z"
last_activity: 2026-04-08
status: executing
stopped_at: Phase 6 complete, Phase 7 discuss pending
last_updated: "2026-04-09T10:20:00.000Z"
last_activity: 2026-04-09
progress:
total_phases: 5
completed_phases: 0
total_plans: 0
completed_plans: 0
percent: 0
completed_phases: 1
total_plans: 2
completed_plans: 2
percent: 20
---
# Project State
@ -21,16 +21,16 @@ progress:
See: .planning/PROJECT.md (updated 2026-04-08)
**Core value:** At a glance, see where your time went -- a visual map of tracking activity that makes patterns obvious
**Current focus:** v1.1 Modes & Filtering -- Phase 6 ready to plan
**Current focus:** v1.1 Modes & Filtering -- Phase 7 ready to discuss
## Current Position
Phase: 6 of 10 (Renderer Architecture)
Phase: 7 of 10 (Mode Switcher + Week Mode)
Plan: --
Status: Ready to plan
Last activity: 2026-04-08 -- Roadmap created for v1.1 (5 phases, 14 requirements mapped)
Status: Ready to discuss
Last activity: 2026-04-09 -- Phase 06 executed and verified
Progress: [░░░░░░░░░░] 0%
Progress: [██░░░░░░░░] 20%
## Performance Metrics
@ -38,7 +38,9 @@ Progress: [░░░░░░░░░░] 0%
- Total plans completed: 11
- Phases completed: 5
**v1.1:** No plans executed yet.
**v1.1:**
- Plans completed: 2
- Phases completed: 1
## Accumulated Context
@ -48,13 +50,14 @@ Progress: [░░░░░░░░░░] 0%
- Week-mode uses client-side aggregation of existing DayEntry data (no backend changes)
- TomSelect must be bundled (not available as Kimai global), deferred to last phase
- Custom controller endpoints needed for entity data (Kimai API routes require IsGranted('API'))
- Kimai plugin PHP files must live at bundle root (not src/) for PSR-4 autoloading compatibility
### Blockers/Concerns
None yet.
None.
## Session Continuity
Last session: 2026-04-08
Stopped at: Roadmap created for v1.1 milestone
Last session: 2026-04-09
Stopped at: Phase 6 complete, Phase 7 discuss pending
Resume file: None