@ -46,8 +46,8 @@ Plans:
|
|||
**Plans:** 2 plans
|
||||
|
||||
Plans:
|
||||
- [ ] 02-01-PLAN.md -- Refactor flag parsing, add --check and --dry-run modes
|
||||
- [ ] 02-02-PLAN.md -- Env audit display with grouping, masking, and confirmation prompt
|
||||
- [x] 02-01-PLAN.md -- Refactor flag parsing, add --check and --dry-run modes
|
||||
- [x] 02-02-PLAN.md -- Env audit display with grouping, masking, and confirmation prompt
|
||||
|
||||
### Phase 3: Sandbox-Aware Prompting
|
||||
**Goal**: Claude inside the sandbox knows it is sandboxed, how to install tools, and what is unavailable
|
||||
|
|
|
|||
|
|
@ -4,14 +4,14 @@ milestone: v1.0
|
|||
milestone_name: milestone
|
||||
status: executing
|
||||
stopped_at: Phase 2 context gathered
|
||||
last_updated: "2026-04-09T14:46:43.217Z"
|
||||
last_activity: 2026-04-09 -- Phase 02 planning complete
|
||||
last_updated: "2026-04-09T15:42:39.135Z"
|
||||
last_activity: 2026-04-09
|
||||
progress:
|
||||
total_phases: 3
|
||||
completed_phases: 1
|
||||
completed_phases: 2
|
||||
total_plans: 4
|
||||
completed_plans: 2
|
||||
percent: 50
|
||||
completed_plans: 4
|
||||
percent: 100
|
||||
---
|
||||
|
||||
# Project State
|
||||
|
|
@ -25,10 +25,10 @@ See: .planning/PROJECT.md (updated 2026-04-09)
|
|||
|
||||
## Current Position
|
||||
|
||||
Phase: 1 of 3 (Minimal Viable Sandbox) -- COMPLETE
|
||||
Plan: 2 of 2 in phase 1
|
||||
Phase: 3 of 3 (sandbox aware prompting)
|
||||
Plan: Not started
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-04-09 -- Phase 02 planning complete
|
||||
Last activity: 2026-04-09
|
||||
|
||||
Progress: [███░░░░░░░] 33%
|
||||
|
||||
|
|
|
|||